Milestone:
|
Essential Artifacts (in order of importance) | State at milestone |
---|---|
Vision | The project's core requirements, key features, and main constraints are documented. |
Business Case | Defined and approved. |
Risk List | Initial project risks identified. |
Software Development Plan | Initial phases, their durations
and objectives identified. Resource estimates (specifically the time,
staff, and development environment costs in particular) in the Software
Development Plan must be consistent with the Business Case.
The resource estimate may encompass either the entire project through delivery, or only an estimate of resources needed to go through the elaboration phase. Estimates of the resources required for the entire project should be viewed as very rough, a "guesstimate" at this point. This estimate is updated in each phase and each iteration, and becomes more accurate with each iteration. Depending on the needs of the project, one or more of the enclosed "Plan" artifacts may be conditionally completed. In addition, the enclosed "Guidelines" artifacts are typically in at least a "draft" form. |
Iteration Plan | Iteration plan for first Elaboration iteration completed and reviewed. |
Development Process | Adaptations and extensions to the Rational Unified Process, documented and reviewed. This typically includes project specific guidelines and templates. |
Development Infrastructure |
All tools to support the project are selected. The tools necessary for work in Inception are installed. In particular, the Configuration Management environment should be set up. |
Glossary | Important terms defined; glossary reviewed. |
Use-Case Model (Actors, Use Cases) | Important actors and use cases identified and flows of events outlined for only the most critical use cases. |
Optional Artifacts |
State at milestone |
Prototypes | One or more proof of concept prototypes, to support the Vision and Business Case, and to address very specific risks. |