Changing job queue entries

 

You can change an existing job queue entry in the specified subsystem description. This command can be issued while a subsystem is active or inactive. To change the job queue entry in a subsystem, use the character-based interface. Command: Change Job Queue Entry (CHGJOBQE)

Example: This command changes the maximum number of jobs that can be active at the same time from the job queue QBATCH in library QGPL. The sequence number of the job queue entry does not change. Up to four jobs from the QBATCH job queue can be active at the same time. Up to one job can be active from priority level 1. There is no maximum for the number of jobs that can be active at the same time from priority level 2. Priority levels 3 through 9 do not change.
CHGJOBQE   SBSD(QGPL/QBATCH)  JOBQ(QGPL/QBATCH)  MAXACT(4)
           MAXPTY1(1)  MAXPTY2(*NOMAX)

 

Parent topic:

Changing a subsystem description

Related concepts
Job queue entry Job queue entries